Menu
Streetwise Answers
I have belatedly taken responsibility for a contract and I am concerned about the current contractual position.
The job is approx. 45% complete and was scheduled to be handed over July 2011 and is now c. 6 months late. I believe that a claim had been submitted for EOT several months ago and failed, which is astonishing given the circumstances and will have to look into the detail.
The issue would appear to have been left to fester and has remained unchallenged for months.
Currently we have no revised contract programme or agreed end date from the main contractor as he is claiming he can't produce one until he gets clarification from the client (which is an invalid reason as far as I am concerned, our contract is with the MC) and are working from what I can see to piecemeal unofficial sectional programmes and are basically at the mercy of the MC and spending the money.
We have not been paid any prelims since last February, not one variation has been agreed and the job is therefore effectively at large.
I believe that at one point we exercised our suspension rights under the contract (FIDIC with some domestic conditions) and withdrew our labour. This did not gain us anything and at best put us further behind in terms of the available access instead of keeping tight.
Clearly we need to get order back into proceedings, therefore any advice you can offer would be greatly appreciated.
Gordon Hill Qatar
Read Answer HereHi Streetwise
I have agreed vos with a clients QS and had response back to say agreed, but now the QS has left and a new QS has stepped in. He has now asked for more information and put them as on account payments.
What do I do?
Also I have another contract which was for 44 weeks and we are now in week 64. Can I claim for extra hire and supervision costs ? I have emailed them on week 50 requesting this but have not had any amswer.
Hope you can help. Good site by the way.
Regards Richard Wattam
Arc Force Ltd
Read Answer HereWe are carrying out a project where an overall programme was agreed
Subsequently several weeks into the project The main contractor introduced a Target Programme which they have not met
In contract law where does a target programme sit. I presume that the the inital agreed programe is the over riding legal document
Joe
ATC Electrical
Read Answer HereThroughout our contract period, our Method Doc was changed to accommodate restrictions of access imposed by the main contractor. Eventually during the progress of the works a methodology was agreed but resulted in a reduction in the content of the testing work.
Post completion and post submission of our documentation , our client has taken the view that our Fixed price Order is now redundant and that he now has the right to modify our contract to a day rate Order based upon his personal appraisal of the time and our costs expended on site . Naturally he has chosen to bullishly ignore management time, supervisory site attendance and our loss of profit and overhead. Our time on site equates to 72% of our maximum time allowance.
We responded initially with a Without prejudice calculated good will offer to settle for 81% of the value for prompt payment, whilst maintaining our entitlement to the full order value.
There has been no dialogue written or otherwise regarding financial reductions during the course of the works.
We now take that the view the full amount is due as we and they made a commercial decision in pricing and their acceptance of our Quotation.
Are we correct in maintaining entitlement
Regards
Rick
Commissioning Specialists
Read Answer HereI am owed a significant amount of retention for various projects for the same Contractor. The total amounts to approx £25k, made up of amounts £25k average. The oldest project is over 3 years ago, the most recent approx 2 years. What is the best way to recover this money if the Contractor either fails to respond or rejects my claim by saying he has not recieved End of Defects/Final Payment from the (his) clients? Andy McDonough Peterborough
Read Answer HereWe have undertaken a £1.9M M&E COntract for a main builder and at Final account stage (after releiving the majority of the project team of their positions) the Main Contractor's Commercial Director has set about the Draft Final Account with a vengeance and is citing the Client and the M&E consultant as the reasons for the 'reductions'.
The work was a design and build contract with a performance specification.
It has dragged on for months and I would like to escalate the process but am not sure which way is best to proceed.
To make matters works, we offered an additional 2.5% discount for 30days payment and he has not once paid on 30days - Am I within my rights to remove this 'discount' on my draft final account.
(Regrettably I was not involved at the outset or during this project, just picking up the pieces!) - Any advice would be appreciated.
Joe Makepeace
M&E Contractor
Read Answer Here
Hi Streetwise
We are working for a Contractor who has deducted monies for cleaning up amounting to over £8k no clean up notices were issued nor any proof of the works having been carried out are they allowed to do this?
We have had the monies taken from our valuations before they are paid.
What advice can you give us?
Clive May
C May Brickwork Ltd
Read Answer Here
Streetwise
We have recieved a collateral warranty for one of our projects using the JCT 2005 Sub-contractor collateral warranty document. We are fine with all of the terms with regards to workmanship, however we used an external designer for the works.
We are being asked to sign for the design competancy, are we able to list the designer within the agreement, or do we need to raise our own internal collateral warranty against the designer?
You assistance would be much appreciated.
Richard Orry WBS Nottingham
Read Answer Here
Hi Streetwise
We bought some profiled metal roofing sheets from Phoenix Fabrications for a job carried out some time ago. Interserve have paid us, we have paid Phoenix however phoenix went into administration last week not having paid their coil supplier, Coilcolor.
We are trying to get the product guarantee from Coilcolor however they are saying that they do not issue guarantees until they have received payment, which now looks unlikely. Where does this leave us, Interserve and the Client? Is there any consumer legislation that we can rely on or are Coilcolor within their rights to refuse?
Eddie Ford Rooksby Roofing
Read Answer Here
Hi Streetwise
We employ approximately 50 staff and our existing offices are effectively based in three adjacent old converted houses.
We are reviewing our fire assessment, evacuation and emergency procedures and want to ensure we incorporate appropriate procedures for Disabled people.
We don't currently have any disabled staff or generally have disabled visitors and have not made any building changes to accomodate disable visitors. Can you advice what we reasonably need to do to satisfy our legal obligations, given there has been no practical issue to date in this regard?
Martin Hartley
Argus Fire
Hi Streetwise,
Can you recommend a good source of information on negotiating?
Derek Turnbull
Ceramic Tiling Contractors Lewisham
Read Answer HereStreetwise can you help?
We have just received a letter from a Contractor telling us that he intends to deduct £65,000 from our account because we have delayed the job.
This is the first time we have heard of any problem!
What should we do?
Peter Hall
Joiners Solihull
Read Answer HereStreetwise
We have been instructed by a Contractor to carry out additional work but his instruction says "This Instruction Does Not Necessarily Constitute A Variation To Your Contract or Entitle you To Payment". We are concerned we aren't going to get paid. Do we have to carry out the additional works?
Jeff Stone - Specialist Roofing Contractors Birmingham
Read Answer HereHello Streetwise,
We are electrical contractors working mostly on large commercial schemes, but we have recently become involved in a housing development which has "penalties" for not completing on time. We have heard of "liquidated damages". Are there ay differences?
John Antrebus,
Electrical Contractors Leeds.
Read Answer HereA-Z of Resources
